RennovEN™

RennovEN Ensure guide

House construction checklist: what to check at every stage, and why

14 stages and 37 key checks our engineers use on residential self-builds, from drawings to handover. Use it with your contractor, or let us run it for you.

Quick answer

What should I check at each stage of house construction?

Check footing size, steel and cover before the footing pour; column and slab steel, stirrups and cover before every pour; curing for 7–10 days; brickwork and lintels; pressure-test concealed pipes and check wire sizes and earthing before plaster; run a 48-hour ponding test before tiling wet areas; and audit the finished house before the final payment.

S0Drawings, BOQ and contract review

When: Before work starts

Structural drawings are complete

Footing, column, beam and slab drawings with bar schedules, signed by the structural engineer.

Why it matters: Without full drawings there is nothing to check the site against, and the contractor decides your steel by eye.

BOQ matches the drawings

Quantities and specifications cross-checked, with brands and grades named for cement, steel, bricks and fittings.

Why it matters: A vague BOQ is where cost overruns and cheaper substitutes come from.

Inspection stages agreed with the contractor

A stage calendar and the notice the contractor gives us before each pour or cover-up.

Why it matters: Work covered before we see it can’t be inspected. Agreeing this on day one avoids arguments later.

S1Setting out and excavation

When: Before footings

Setting out matches the plan

Centre lines, diagonals and plot setbacks measured on site.

Why it matters: A building set out wrong by a few inches can breach setbacks or misalign every room above it.

Excavation depth and bed

Depth and width checked against the drawing; bed levelled, rammed and free of loose soil or water.

Why it matters: Footings on loose or wet soil settle unevenly, which shows years later as cracks across the house.

S2Footings and PCCEssential

When: Before the footing pour

PCC bed and footing size

Plain concrete bed laid level; footing dimensions measured against the drawing.

Why it matters: Undersized footings carry more load per square foot than designed. It can’t be corrected once the house stands on them.

Footing steel and cover

Bar diameter, spacing and count checked against the bar schedule; cover blocks of at least 50 mm under the mesh.

Why it matters: Steel in contact with soil rusts. Cover is the only thing protecting it for the life of the house.

Column starter bars

Starter bars positioned, plumb and tied to the footing mesh.

Why it matters: A misplaced starter bar means every column above is off-centre.

S3Plinth, anti-termite and DPC

When: Before plinth filling and the first wall

Anti-termite treatment

Pre-construction chemical treatment of the soil and plinth, witnessed and logged.

Why it matters: Termites destroy door frames, wardrobes and kitchens from below. Treatment is cheap now and expensive later.

Damp-proof course (DPC)

A continuous DPC at plinth level under every wall.

Why it matters: Without it, ground moisture rises into walls and peels the paint at skirting level for the life of the house.

Plinth filling compacted

Filled in layers, watered and compacted.

Why it matters: Loose filling settles and the ground-floor tiles sink and crack.

S4ColumnsEssential

When: Before each column pour

Steel matches the drawing

Bar diameter, count, lap position and length checked against the schedule; TMT grade and ISI marks seen on the bars.

Why it matters: Columns carry the house. A missing or thinner bar isn’t visible again until something fails.

Stirrups and hooks

Stirrup spacing per drawing and 135° hooks for earthquake-resistant detailing.

Why it matters: Stirrups hold the column together in an earthquake. Lucknow is in seismic zone III.

Cover and plumb

Cover blocks of at least 40 mm on all faces; shuttering plumb and braced.

Why it matters: Too little cover lets moisture reach the steel. It rusts, swells and cracks the concrete off within 10 to 15 years.

S5Beams and slab (every floor)Essential

When: Before and during each slab pour

Slab and beam steel

Main and distribution bars, extra bars at supports, chairs and cover blocks checked against the drawing.

Why it matters: Steel placed too low or too high in a slab loses much of its strength. You can’t see it once it is poured.

Shuttering and levels

Props, levels and slopes checked; sunken areas for toilets formed.

Why it matters: Sagging shuttering gives a wavy slab and a heavier floor. Wrong slopes give ponding terraces.

Pour day

Mix and water content, vibrator in use, no long delays between batches. Cube samples taken if agreed.

Why it matters: Extra water and poor compaction make weak, porous concrete with honeycombs, which no plaster can repair.

Conduits and sleeves in the slab

Electrical conduits and plumbing sleeves placed before the pour.

Why it matters: Forgotten sleeves mean cutting through a cured slab later.

S6Curing and de-shuttering

When: In the days after each pour

Curing log

Kept wet for at least 7 days (10 for PPC or blended cement), with ponding on slabs.

Why it matters: Concrete gains strength by curing. Short curing means surface cracks, roof leaks and lower strength.

Surfaces after de-shuttering

Honeycombs, exposed steel and cold joints recorded before anything is plastered over.

Why it matters: Plaster hides honeycombs in a day. Once hidden, they are water paths to the steel.

S7Masonry and lintels

When: During brickwork on each floor

Bricks and mortar

Bricks soaked, joints filled and staggered, mortar mix as specified.

Why it matters: Dry bricks suck water from mortar and the joints never bond, which causes cracks and damp.

Walls plumb and in line

Plumb bob and line on every wall.

Why it matters: Out-of-plumb walls need thick plaster to hide them. Thick plaster cracks and hollows.

Lintels and bands

Lintels over every opening with bearing on both sides; bands where the drawing shows them.

Why it matters: Missing lintel bearing causes the diagonal cracks above doors and windows.

S8Concealed plumbing and electricalEssential

When: Before plaster closes the chases

Pipes pressure-tested

Concealed water lines filled and held under test pressure, joints inspected, before chasing is closed.

Why it matters: A weeping joint inside a wall shows up months later as damp, behind tiles you then have to break.

Drain slopes and traps

Slopes, traps and cleanouts in sunken areas checked.

Why it matters: Flat drains block and back up. Missing cleanouts mean breaking floors to clear them.

Conduits, wire sizes and earthing

Conduit routes and boxes; wire sizes per circuit (1.5, 2.5 and 4 sq mm); ISI-marked wire; earth pit and earth continuity.

Why it matters: Thin wire on an AC or geyser circuit overheats. A missing earth is a shock risk for decades.

S9Plaster

When: During internal and external plaster

Thickness and mesh at joints

Thickness within spec; chicken mesh where brick meets concrete.

Why it matters: The brick-to-concrete joint is where hairline cracks appear in every new house unless it is meshed.

Hollowness and curing

Tap-tested for hollow patches; cured for the specified days.

Why it matters: Hollow plaster falls off. External plaster that isn’t cured cracks and lets rain in.

S10WaterproofingEssential

When: Before tiling toilets, balconies and the terrace

48-hour ponding test

Sunken toilets, balconies and the terrace are flooded for 48 hours and the ceilings below are checked.

Why it matters: This is the only moment waterproofing can be proven. After tiling, a failure means breaking everything again.

Corners, pipes and upturns

Coving at wall-floor joints, collars around pipes, upturn on walls.

Why it matters: Waterproofing fails at corners and pipe entries first.

Terrace slope and outlets

Slope to every rainwater outlet; outlets sized and grated.

Why it matters: Ponding on the roof is the main cause of top-floor ceiling leaks.

S11Flooring, tiling, doors and windows

When: During finishing

Tile bedding and slopes

Tap test for hollow tiles; slopes to drains in wet areas; grout and lippage.

Why it matters: Hollow tiles crack within a year. Wrong slopes leave water standing in toilets.

Door and window frames

Frames plumb, fixed and sealed; termite treatment on wooden frames.

Why it matters: Unsealed frames let rain into walls; misaligned frames make doors stick for good.

S12Painting, fittings and services

When: Before handover

Brands and grades as contracted

Paint system, sanitaryware, CP fittings, switches and wires matched to the BOQ.

Why it matters: Finishing is where cheaper substitutes are easiest to slip in, and you paid for the better brand.

Services tested

Every point, tap, drain and fixture working; distribution board labelled; RCCB trips.

Why it matters: It is the last chance to have the contractor fix what doesn’t work at no cost to you.

S13Handover auditEssential

When: Before the final payment

Full RennovEN Certified checklist

Every room, zone by zone, with moisture, thermal, earthing and tap tests.

Why it matters: One last, complete look with instruments before the contractor leaves and before you pay the retention.

Home Health Score and issue log

A score out of 100 and a severity-sorted issue log for the contractor; re-check of fixes.

Why it matters: A clear, scored baseline for the house. It is also what lets you join RennovEN Secure with no inspection.

The handover audit uses the full RennovEN Certified pre-possession checklist.

General guidance for residential RCC-frame houses. Your structural drawings and the engineer who signed them take precedence over any general checklist.

Get an engineer on your side before the next pour

Stage-by-stage checks, photo reports, a scored handover audit, and RennovEN Secure with no inspection.

Start My Build with Ensure

Priced by constructed area · Quote first

WhatsApp us

Ready to find out what your home really needs?

Start with a free, itemised quote. No guesswork, no obligation.

Start My Build with Ensure

Priced by constructed area · Quote first

WhatsApp us
Start My Build with Ensure